1039 Meters! China's Shale Gas Horizontal Well Drilling Daily Footage Sets New Record
Dec 16, 2023

At 8:00 on December 15, Well Ning 209H73-5 of Southwest Oil and Gas Field Company completed 1,039 meters of footage in a single day while drilling from the deflection section to the horizontal section of the 215.9 mm borehole Longmaxi Formation. The daily drilling footage exceeded the 1,000-meter mark for the first time. , breaking the previous Chinese shale gas single-day drilling footage record of 828 meters in Well Ning 209H47-10. The average daily mechanical drilling speed of this well reached 66 meters/hour, and the drilling encounter rate of the "platinum target body" was 100%.
The Ning 209H73 platform is a stable production well platform deployed by Southwest Oil and Gas Field Company in the Ning 209 well area. It adopts a "daily fee" management model and is drilled by Bohai Drilling Engineering Company. Southwest Oil and Gas Field Company gives full play to the "oil company" model, adheres to the leadership of Party A in engineering technology, coordinates the resources of all parties, deeply promotes the integration of geology and engineering, and constantly challenges the limit of drilling speed increase.
The first is to "select the best and the fastest" to lock the "double sweet target body" of the drilling project. Precise geological modeling and "smart experiments" were carried out to select a 1-meter target with high mechanical drilling speed and low vibration of the rotary guide tool within the 4-meter "platinum target", and accurately control the well trajectory within the "double-sweet target" travel through.
The second is to optimize drilling technology and improve drilling efficiency. Tailor-made PDC drill bits with strong attack and high stability are selected, and rotary steering tools and high-torque screws are selected to improve the rock-breaking efficiency of the drill bit; drilling parameters are strengthened, and high drilling pressure, large displacement, and high-speed drilling are used throughout the process; standardized column connection operations are formulated The regulations are timely and the time for picking up the posts is shortened from 30 minutes to 8 minutes.
The third is to monitor the wellbore safety status in real time. Using advanced simulation software, the drilling optimization center simulates the bottom hole equivalent density and friction coefficient in real time, monitors the cleanliness of the wellbore, and reduces the complexity of drilling; correctly identifies drilling cuttings gas, unifies the understanding of all parties, and achieves safe and fast drilling under high total hydrocarbon conditions.
In the next step, Southwest Oil and Gas Field Company will continue to strengthen management, drill the remaining horizontal sections as quickly as possible, and strive to control the entire well drilling cycle within 15 days.